House Assembly construction phases


1

Preparing for the base layer of the building by means of SILICAWOOD® panels connected by rectangular hollow core aluminum profiles inserted into the joint female-female side.The panels are arranged in the direction of the main east-west axis. The width of the each module is equal to 120 cm and the thickness is 18 cm.

2

Assembling peripheral load bearing walls SILICAWOOD®; modules of 120 cm wide and 15 cm thick prefabricated of site (total 22 elements ) Connected by rectangular hollow core aluminum profiles inserted into the joint female-female side and through self taping wood screws . The same joint applies for the connection between base slab and walls .

3

Fitting the Bay Window panels and the internal walls (9 elements).

4

Positioning the second layer of the floor base with the function of the internal substrate, into which the distribution ducts will be built in for energy and water.

5

Inserting the internal division panels made of SILICAWOOD®.

6

Positioning of technological BB BOX rainwater collection tank

7

Anchoring interior horizontal wooden beams for supporting the roof.

8

Laying roof cover panels prefab on corrugated metal sheets with lattice ventilation spacers incorporated The roof panels are jointed in the same way as the walls.

9

Anchoring the external roof covering in corrugated sheet metal.

10

Plastering external internal walls and concrete floor jet pigmentated.

11

Installation of doors and and windows

12

Positioning solar panels, terminal for swuage systems and external gutters coveres and wooden window grides

13

Layout of the fence basement

14

Layout of the SILICAWOOD® fence panel fence

15

External Painting and final touches